Schedule
A simple list of what’s coming up. Anyone on the team can add or update items via the form at the bottom of the page (in v2).
Next up
(populated after Dave’s review and the first round of phone calls)
Call Polk County about the permit
- Owner: Dave or Eli
- When: Within the first week the site is live
- What: Phone 503-623-9237, give the property address, ask for the existing septic permit file. Capture: permit number, original issue date, permitted design type, current legal status, renewal or reapply path.
Eli’s first inventory pass
- Owner: Eli
- When: Within two weeks of the Polk County call
- What: Walk the septic site. List what’s installed (tank? lines? drainfield?), what materials are on hand, what’s missing. Photos of each.
First advisory visit with Cody and Russell
- Owner: Dave coordinates; Cody and Russell visit
- When: After Eli’s inventory; ideally a Saturday so everyone can be there
- What: Walk-through. Confirm what we have, what we need, what order to do it in. Decisions get logged.
Begin the install
- Owner: Eli + Dave
- When: As soon as advisory visit + materials list is settled
- What: Whatever Cody and Russell said first.
Mid-work review with Cody and Russell
- Owner: Eli arranges
- When: Partway through the install
- What: Catch our mistakes before they’re buried.
Finish the install
- Owner: Eli + Dave
- When: ?
- What: Backfill, restore site, prep for inspection.
Polk County inspection
- Owner: Dave or Eli requests
- When: Within Polk County’s scheduling window after install is complete
- What: Sign-off.
Tower construction resumes
- Owner: Dave + Eli
- When: Post-inspection
- What: Separate workstream from here on.